Nancal Electric Supports Successful Completion of Phase I RCP Drive Localization Retrofit at Haiyang Nuclear Power Plant

Publish Time: 2026-04-10     Origin: Site

On April 9, 2026, the fifth refueling outage of Haiyang Nuclear Power Unit 1 was successfully completed, concluding with the full localization replacement of the remaining four imported RCP Drives. The unit was successfully reconnected to the grid on its first attempt.

With this milestone, all eight imported RCP Drives across the two units of Haiyang Nuclear Power Phase I have now been fully replaced with Nancal Electric medium voltage drives, completely eliminating unplanned shutdowns caused by RCP Drive fault and providing a critical equipment foundation for safe and stable unit operation.

The RCP Drive system adopts a "4-operation and 1-standby" configuration. In the event of a failure of any RCP Drive, the hot standby drive can automatically take over quickly, significantly improving the reliability of the RCP power supply and substantially enhancing unit operational reliability and economic efficiency. Nancal Electric supported project implementation with professional, efficient, full-process technical services, contributing solidly to the localization of nuclear power equipment and energy security with reliable products and quality service.

Source: Shandong Nuclear Power Company Ltd. Official WeChat Account

Nancal Electric Powers New Unit Commissioning at Guangzhou Compressor Station

Nancal Electric Supports Successful Completion of Phase I RCP Drive Localization Retrofit at Haiyang Nuclear Power Plant

SPIC Completes Full Localization of Reactor Coolant Pump Drives at Haiyang Nuclear Power Unit 2

Hydrostatic Test Successfully Completed for Reactor Coolant System of Haiyang Nuclear Power Unit 3

Nancal Electric Successfully Co-organized the 10th National Petrochemical Electrical Technology Conference 2026